I am trying to add the typical category of "glazing" to a door schedule, but when I add a door with glass into my project, I cannot make this information show up on my schedule. I need typical information such as "!/4" Temp" and "1" Insul" under the category of glazing. I added the "Door: Glass" heading in the schedule, but nothing appears when I add a glass door into the project. I was able to easily do this in AutoCAD Architecture.
How can the dimensions for the system family door be shown in the door schedule?
I tried to make a instance paramater, type parameter, both through shared parameter for the doors in the family file, but they are still not showing up.
So I've created a door schedule and added all the parameters I needed. But to get the "room name" to list and be associated with the door tags I had to choose either if the doors were going to a room or from a room, so I chose to, however, some of the doors swing are leaving the room so instead of tagging them with the corridor we want them associated with the room. But I can't edit the column the room names are in. If I click on a cell it gives me a drop menu on the side of what I can choose for that cell and it doesn't have the listed room that I need. It does not let me just type in the cell is there a way to fix this?! The blue highlighted name shows my option of what I can list as the room name or I can leave it blank, it lets me click inside the cell as if I could just put text in it but it actually doesn't show anything that I type.
Currently our door schedule populates when the doors are inserted into the drawing. I would like to know if I can set the schedule up so it populates when the door is tagged. Our doors are inserted into a base plan and that base plan is xrefed into various sheets.
The doors are tagged in one of these sheets and not the base plan. It takes too much time to stop and set up the schedule to schedule the doors across the xref for every project we do. I have read several articles but none of them explain how to schedule from the tag that I can see. I thought this was how the schedule was set up in a previous version.
--Is there a way to do a door schedule by styles rather than individual door?
--To clarify: I want my door schedule to create a new door number only when one or more of the property sets, classifications, or door styles pertaining to a door are not defined by other doors in the schedule. This would facilitate giving the same door number to multiple doors that have matching schedule information, and cut down on my schedule size.
--how to do this. If I need to create custom tags, schedules, or formula properties.
Working on a project with a green house. I created a roof using "roof by footprint". I selected "sloped glazing" and assigned mullions for the various conditions as well as spacing.
The walls below are curtain walls. When I create the roof, the mullions are oriented the wrong way. How do I control the orientation of the mullions?
In desperation, I mirrored the roof about a vertical axis. See images below.
This corrected the orientation for me, but I must believe there is a better way! A "proper way"... Did I miss something in the initial creation of the roof? I changed the sloped glazing of the roof to a basic roof. When I do this I notice the roof moves up.
I assume this is when the orientation of my roof inverted...
I made a metal standing seam roof by putting mullions on sloped glazing roof. Is there a way to extend the mullions past the edge of the perimeter of the roof?
I am using groups for each type of apartment in the project i am doing, Some groups are mirrored, In my door schedule i added a parameter (instance) for my door orientation (Left or right orientation). The problem is when i note a door ina group as left and the same door in the mirrored apt needs to be right it keeps the same note for each door as it thinks the group in not mirrored.
Is it possible to make the graphic represention of a component in a schedule (make a legend component representation a parameter) or use legends dynamically. I would like to schedule all the casework with quantities of each component. But the current schedule has a graphic representation next to the quantities but it is not in revit and the quanties are determined manually by counting them. I know there is a add on you can purchase to create dynamic legends but is there a way to do this directly in Revit?
I have created a operable window to insert in a curtain wall system based on the "Window - Curtain Wall" family. I created a simple extrusion for the glazing panel and assigned it the subcategory of "Glass". When loaded in the project, the cut lines of this panel are a much heavier weight than mullions, other glass panels, etc. The lines are so thick, the double line just becomes a fat single line as they merge together. Adjacent glass panels don't have this line weight problem. I can find no override or other control/parameter that fixes this.
I am having trouble trying to edit the title fonts in a door schedule. No matter which font I pick under "Edit Schedule Table Style" after a selection of the schedule and right clik, the title font will not change. The listed doors font does change. Is it not poosible to change the title and descriptor font?
how to link a door frames width and height to the door schedule? For example if I have a 3'-0" x7'-0" door the frame width would be 3'-4"x7'-2", I would like this to automatically generate in my door schedule when I insert a door without me having to manually put it in. I am using AutoCAD Architecture 2010.
We have a custom built schedule which has the typical "Comments" field. As we aork in our project and add items to that particular row, the "Comments" field gets reset to be blank.
What we are trying to do in effect is to establish a reference point so the we know where we are in relative to the reference point.
Is there a way to make the "Comments" field stick?
is there any way to schedule objects by id number?, maybe through a formula within the schedule that may call the id or the revit API and if that is the case
I've been trying to style my sheet list schedule. ... trying.Is it true that I can't
* style (fontsize, fontweight etc) a 'sorting header'? * style the scheduleborder to only underline the sheetlist-rows * seperate the header styles from sheetlist styles? (I don't want the header to have a border.... while sheetlist-row should be underlined) * format the height of a row