Apr 3, 2012Is it possible to generate alignment chainages at irregular (not-constant) intervals?
View 2 RepliesIs it possible to generate alignment chainages at irregular (not-constant) intervals?
View 2 RepliesHow do i make my chainages show as 420.000 rather than 4+20.00.I.e I need to take the plus sign out (we never use them - only whole distances) and I need it in 3 decimal places.
View 3 Replies View RelatedIs there a way to change the format of alignment chainage from 1501+120 to this format 1501km120?
View 3 Replies View RelatedIt must be the medication, but I just can't remember something I learned in the last couple weeks regarding contour label intervals. I've been using C3d 2013 for about a year now and had used LDD 2004 until the upgrade. I've become pretty comfortable with the styles based implementation now.
What exactly controls the numeric value shown in a contour label? I've got them looking fine on my site. I imported my styles and settings to a coworkers site but for the life of me I cannot remember what I had to change to get the contour labels to show increments of 1 foot (they were showing fractions of a foot)… Typing the word "fractions" triggered my recall. The problem and solution was in the drawing units.(Inches vs feet).
How much time I spent looking through the style settings in search of the one setting I was missing... both times! One of the best ways to push things from short term memory into long term memory is "Increased active practice".
One thing I learned this time: The style settings are not always the source of the problem. It could be something very basic. It may save time to check the basics first.
Windows 7 Professional 64-bit - Service Pack 1
Intel﴾R﴿ Core﴾TM﴿ i7-3820 CPU 3.60GHz; 16 GB DDR3 Dual Channel RAM
nVidia Quadro 4000; AutoCAD Civil 3D 2013, sp1
I've drawn a profile and would like to show the elevations of each surface selected in different bands. I've set up the bands easily enough though when they display on the section I've got two levels either side of the chainage line one with 0.01 precision and one with 0.001 precision - I only want to display one. I've tried fiddling with the Profile View Properties but don't seem to be getting very far..
View 3 Replies View RelatedI'm working on a permit where I need to display topographic contours, but have different maj/min intervals depending on the slope of the topography. To me, this seems a little strange and makes for misleading information, but it's what the permit requires.
I'm covering a roughly 5000 x 5000 sq ft area with a partially built landfill on it and a rather changing surrounding topography.
We design a lot of Waste storage facilities, mainly above ground level. I need to generate stage storage volumes at one metre intervals. Is there a way to automate this?
View 6 Replies View RelatedI was wondering how I can set my Elevation Text and Profile Major Gridlines at different intervals? It seems like there stuck to one another.
For example, I want my Major Gridlines at every 1.0m but show elevation at every 5.0m.
I tried 'splitting' the profile view with a hacked up style but it seems to be messing up my pipes. Is there a way I can make a vertical band of some sort?
Civil 3D 2011
Win 7
Intel Xeon 3.20GHz
15Gb Ram
Quadro 600
This is a problem that comes from previous versions. When applying a figure using Wrap resource to a Paragraph Text in columns: most of times the basis of the text is not aligned correctly.
View 2 Replies View RelatedI need cross section information of a creek for a Hydrology program (DRAINS in Australia) and need to extract this from a surface I have created in Civil 3D. I require the Chainage and Level for a profile which represents the creek cross section at several specific locations. The information is essentially the data bands in a Profile which I can create, however I cannot see how to obtain this information in a form I can use.
the format of the data can be copy and pasted into Excel from which I can directly import the information into the software.
When labeling pipes in a pipe network; is there a way or expression to roundup the label to 6 inch interval. For example, if I have a pipe length of 2.6 feet, I want to roundup this to 3.0 feet and if I have a pipe length of 2.4 feet, I want to roundup this to 2.5 feet.
View 7 Replies View Relatedi've made a serpantine curve that starts from one line of alignment and end on the other line.
i wanted to know how can c change alignment direction when these two feature line and alignment meet each other in order to change the alignment path?
I using a data reference/shortcut to properly label an alignment in paperspace. However when I reference the alignment in and apply the labels the aren't the same as the original alignment that I am referencing. Is there a setting where I am supposed to apply a new beginning station.
Also it seems as though the stationing(distance) isn't even matching up 1:1 with the original drawing. For example in the original base drawing my alignment starts at 10+00 with the next PI at 14+76.98, but the stationing on the reference alignment starts at 0+83.33 with the very same PI being labeled as 1+23.08. So the very same distance is 476.98' in the real design and the drawing it's being referenced in, but the stationing of the referenced alignment shows it as 39.75 Units.
I've attached a screen of the beginning of the alignment.
Civil 3D 2012
Windows 7 Service Pack 1
Intel Core i7-2600 CPU
16GB RAM
Using Civil 3d2012, Is it possible to change the alignment label style set after the alignment has been created? For example, for an alignment that was created with alignment label set X - change the label set to alignment label set Y? It seems like this should be pretty easy, I must be missing something obvious.
View 2 Replies View RelatedI have a question on Alignment PI's. (Point of Inflection/Intersection)I have an alignment where some PI's have curves, others are merely hard bends.
Is there a way to automatically label the PI's even if they have an associated curve? (I'd like PI, PC and PT)Alternatively, can I only show markers at PI's without curves?
I'm trying to edit some existing alignments. When I create new entities, they do not show up in the alignment grid view. Why is this?
Windows 7 x 64 bit
NVidia Quadro 2000 Dual Monitor
6.00 GB RAM
Intel Xeon W3550 @ 3.07 GHz
Civil 3D 2013 SP 2, Civil 3D 2012 SP2, Civil 3D 2011 V3, Civil 3D 2010 V3
Launching alignment grid view/alignment entities,
I’m wondering if there is a way to launch alignment grid view/alignment entities (attached) without the need to first launching “alignment”? This dialogue box is quite essential in editing the values of radius, degree of curvature and deflection angle for the selected curve.
Can I inherit the station from one alignment as the begin station for another alignment?
For example. Alignment 1 is 1000 ft long and starts at sta 0+00.
At sta 8+01, Alignment 2 begins and goes off in another direction.
I manually enter 8+01 for begin station Alignment 2. Life is good. Still in the design stage, and customer needs to modify Alignment 1 to avoid something. Now Alignment 2 intersects Alignment 1 at sta 8+15, but same N/E coordinates.
I manually enter 8+15 for begin station Alignment 2.
It would be better if Alignment 2 could inherit the begin station based on the new stationing from Alignment 1.
How could make big size pipe with irregular section shape by using Civil 3D?
View 5 Replies View RelatedHow could make big size pipe with irregular section shape by using Civil 3D?
View 3 Replies View RelatedAny lisp programme for creating a line profile and chainage. I have attached a sample drawing. The blocks on the line have elevation and lines are drawn from the datum .If i manually draw it will take too much time.
View 9 Replies View Relatedi need to Create aligned CS line with increasing Chainage Number and Name through a center line (yellow line). The CS lines are 25 meter apart, it can be done by ME command, but can not automatically increase the Chainage number and CS number.
the CS number (CS-1200) is increasing by 1, like CS-1200, CS-1201, CS-1202, ....also The chainage number (CH Km 29+975) is increased by 25, Example: CH Km 29+975 , CH Km 30+000, CH Km 30+025, CH Km 30+050....
i would like to do it automatically, otherwise i have to keep editing for a long time,
I imported Google earth surface (at eye alt 600m) to civil 3d 2012 and created an alignment of length 181m.
When I exported same alignment to Google earth , it showed the length as 190m ( the difference increases with increase in length of alignment) And also the profile view of the alignment in the Civil D & Google earth varies.
I have a an angular polyline (not horizontal or vertical). I want to equally divide the polyline with a specified length and get all separation co-ordinates at each interval. The line remains as polyline, I need to get only the co-ordinates of all the possible divisions for a given length.
I need a C#.Net function for this.
I am looping through the civilapplication.activedocument's alignmentIDs collection and looking to see if the name of the alignment is the one I want.
Is there a more direct way, where I could use the name like
doc.GetAlignmentId("somename")?
maybe GetAlignmentIds() is only way to access the align collection though,
[URL]........
I thought that finding the alignmentId, and using the
doc.GetAlignmentIds().Remove(delId);
would do it.
I know i have the right alignmentId, it all cheaks out, there must be something I have to do after removing from the ID collection.
I am doing a Tr.Commit(); but that does not seem to be good enough.
full code is: (_returnMsg is a local var for the class containing this method)
public void DelC3DHAlign(string name) { _returnMsg = "Error, No alignments available";
//access Civil 3D
CivilDocument doc = CivilApplication.ActiveDocument;
try { using (Transaction tr = HostApplicationServices.WorkingDatabase.TransactionManager.StartTransaction
[Code]....
[URL]....
How is possible to get Cant values of Rail type alignment in C# or VB?
View 2 Replies View RelatedI have a project that comes and goes. It was actually started in Softdesk. Right now I'm working in Civil 3D 2012. I have an alignment that represents the left edge of pavement. Although I'm calling an offset alignment. It was created before they existed. So it's not linked to the centerline. There have been many changes to it over the past few years. Now it has a problem.
I wanted to edit in the Panorama. Right-click > Edit Alignment Geometry > select Alignment Grid View from the Alignment Layout Tools. When I went to the last segment in the Gird View, which was near where I wanted to edit, a segment about two thirds of the way along the Alignment was highlighted. Further investigation showed that although the whole Alignment would highlight when selected, all commands said the Alignment ended much sooner than the end station.
I've found that that alignment has been broken for quite a while but was intact at one time. My question is - What's the best way to repair/recreate it. I know I can explode it and create a replacement Alignment from the resulting entities. But is that the best way?
Civil 3D 2012 SP 2.1
Dell Precision T7400
Xeon CPU 3.16 GHz
Nvidia Quadro FX 4600
12 GB RAM
Win 7 Pro, 64-bit
This is strange. I wanted to label just the alignment name in a couple of places. I have an Alignment Name Label Style that does this. I now notice that it will capitalize some of the lower case P's in the curve label. Not the line label just the curve. They're applying the same style. It also changes back to lower case if I drag the label.
The style has one component and that is the Alignment Name and has Preserve Case set.
is there a way to trim an alignment?
View 3 Replies View Related. How to assign proposed elevation to layout alignment along each station?. I know there is a way in LDT to assign proposed elevations to s specific range of stations or the full alignment, under menu "profiles/ FG Vertical Alignments/Create COGO Points" I am looking for the same one in C3D.
2. How to add connecting alignment label and station in profile view. For example I have an main alignment and in-between lot of other alignments are meeting with this alignment.